May 2025 Update

1 May 2025

Scope of Work:

  • A 1.5km section from Hardys Road northwards to Sports Complex Avenue
  • Widen a 0.5km section from Hardys Road to Montgomery Road to a uniform width of 6.0m with a bitumen seal and 0.5m gravel shoulders.
  • Upgrade the intersection with Montgomery Road including pavement, drainage and a streetlight.
    (Please note: A separate project has added a public toilet in the Montgomery Road car park.)
  • Between Montgomery Road and the Penguin Mountain Bike Park, the existing 0.6km sealed road already meets the required 6.0m width. No upgrade is planned for this section.
  • From Penguin Mountain Bike Park to the Sports Centre opposite Leatherwood Drive, a 2.0m wide concrete footpath will be constructed, and the Sports Complex Avenue intersection will be upgraded.

Progress:

  • Work has not yet commenced within this section.

For further technical information on Section 1 refer to Engineering Drawings.