2023-2024 Project Timeline

1 May 2023

  • Principal Design Consultant (PDA) engaged and site survey undertaken
  • Targeted stakeholder engagements

Preliminary design completed (Sections 1 and 2)

  • Community Information Session held
  • Design report and detail design completed

Request for Tenders for construction issued to industry

  • Final design completed (Sections 1 and 2)
  • Construction tenders evaluated

Preliminary design completed (Section 3)

  • Construction contract awarded to Hardings Group (TAS) Pty Ltd
  • Final design (all stages) revised and issued for construction
  • Pre-construction planning

Construction commenced within Stage 3 (gravel section above Gnomon Farm, through to the Dial Range Carpark (Mount Gnomon).